Cleaning the entire area to remove all loose particles with the help of wire brushes. |
• |
Preparing the surface to receive gunite. |
• |
Reinforcing the surface with welded wire mesh size of 100 x 100 x 10G and anchoring it with 2-½ ft. center to center. |
• |
Cleaning of the surface with water under compressed air pressure before gunniting. |
• |
Apply an average thickness of 50mm gunite on surface ratio of 1:3½, one part ordinary Portland cement and three half-part course sand by volume under compressed air pressure. |
• |
Cleaning of the mulba and staking outside within 20m distance. |
• |
Curing of the surface for seven days. |